Phase #1 area is now ready for service.
Phase #2 is currently in network splicing and testing, getting ready to activate service.
Phase #3 has crews currently pulling fiber through ducting to prepare for network splicing and testing.
Phase #4 has mainline and residential construction drops in-progress.
Phase #5 has mainline and residential construction drops in-progress.
Phase #6 is under initial construction.
Review our Installation process including the preparation and planning needed to complete expansion of our network.
Before Reedsburg Utility / LightSpeed can begin construction, we require the property owner to fill out and supply an application for service.
Before we can begin underground work, we require a map showing relative locations of all private facilities and equipment in potential construction paths.
The drop fee payment is required along with the map and application in order to be added to the construction list.